In this £500,000 contract, John Perkins Construction transformed Grade II Curtilage Listed pig barns into a contemporary, high-end office space for engineering consultancy Hydrock.
Carried out over 12 weeks, the project involved working within the live environment of Hydrock’s main office complex. Disruption was minimised through careful segregation, plus extensive communication with Hydrock staff and other key stakeholders.
Conservation issues were also a priority. The roof and the existing timbers needed to be retained, and specialist tiles were required in order to adhere to conservation regulations. Even in instances where new elements were introduced, the refurbishment was carried out in conservation style, with an emphasis on exposed stonework and timbers.
The resulting characterful office space was delivered on time and on budget, to a high standard.
Client: Hydrock
Value: £500,000 Refurbishment
Duration: 12 Weeks
Type of contract: Competitive Tender
I have found John Perkins Construction professional and easy to work with, producing good quality workmanship, while helping us achieve the cost we needed to.
Dave Lawes
Director, Programme Delivery
Hydrock